I. Acceptance requirements
1. Check appearance
Check whether the finish of the workpiece meets the requirements of the drawing.
Check whether the workpiece is damaged, rusted, bruised, and whether the thread shape and Angle are correct.
If the above problems are found, a detailed record should be made for inspection.
2. Quantity acceptance
Strictly check the drawings, according to the supply contract and processing documents, check the material, specifications and quantity of the workpiece, and accept the workpiece one by one.
Make a record of quantity acceptance, indicating the acceptance place, time, participants, model, product name, fulfilled quantity and actual arrival.
3. Quality acceptance
Assembly shall be carried out in strict accordance with the general assembly drawing and procedural requirements.
Records should be carefully made during quality acceptance. If there is a quality problem with the workpiece, the contractor shall be notified of the details in writing. According to the actual situation, decide whether to return or replace.
If there are special requirements, the processing unit can be found to accept and assemble, and the acceptance document can be signed after the installation is qualified.
2. Acceptance procedures
After the mechanical workpiece is received, the full-time acceptance personnel of both parties shall check and accept the material, specifications, models and quantity of the workpiece according to the contract requirements and the drawings.
The acceptance period is usually 1-2 days. Special cases depend on the effect of use. If there are quality problems, the processing unit can return the goods and claim for compensation, and the processing unit shall bear economic losses.
The general processing contract is not signed by the production department, and the user department directly accepts and fills in the acceptance report.
For the parts that fail to pass the acceptance inspection, the acceptance inspection personnel must handle the overhaul and return procedures within the specified acceptance period.
Special precision workpiece acceptance, by the full-time acceptance personnel to organize the relevant personnel joint acceptance, and fill in the detailed acceptance report. The acceptance of unqualified parts should be filled in the report form in detail, as a condition to improve the processing accuracy, and determine the direction of the future selection of outsourced processing parts manufacturers.